MIME-Version: 1.0
Date: Sat, 23 Aug 2025 16:39:57 +0100
From: andre.eko@matech-cameroun.com
To: Charles Gnouve <charles.gnouve@ihstowers.com>
Cc: bate.agbor@ihstowers.com, moise.moukala@ihstowers.com, 'Evelyne Ngonsog'
 <evelyne.ngonsog@ihstowers.com>, 'Vensa Mohamadu'
 <vensa.mohamadu@ihstowers.com>, lilian.vensu@matech-cameroun.com, 'Amza
 Njatono' <amza.njatono@matech-cameroun.com>, 'SyprienTanzi'
 <syprien.tanzi@matech-cameroun.com>, 'JUDICAEL BATCHAGNIA'
 <judicael.batchagnia@matech-cameroun.com>, 'Konkep Stephane'
 <stephane.nkonkep@matech-cameroun.com>, 'Herve Iroume'
 <herve.iroume@matech-cameroun.com>, "'Alphonse K. Deufo'"
 <alphonse.deufo@ihstowers.com>, 'Dominique Assako'
 <dominique.assako@ihstowers.com>, Jules Sagwa
 <jules.sagwa@matech-cameroun.com>
Subject: Re: MOM between IHS CENTER - MATECH
In-Reply-To: <013301dc1443$86868740$939395c0$@matech-cameroun.com>
References: <CWLP265MB04209560741C788CB5257392FD2CA@CWLP265MB0420.GBRP265.PROD.OUTLOOK.COM>
 <040701dc0854$133815b0$39a84110$@matech-cameroun.com>
 <000901dc0dd6$c2f8f410$48eadc30$@matech-cameroun.com>
 <013301dc1443$86868740$939395c0$@matech-cameroun.com>
Message-ID: <414b4f98c9963f575dacf5a8814a03ef@matech-cameroun.com>
X-Sender: andre.eko@matech-cameroun.com
Content-Type: text/plain; charset=UTF-8;
 format=flowed
Content-Transfer-Encoding: 8bit

Hi Charles;

We need your support for the validation of tanks PM the rate is still 
low

Regards

Le 2025-08-23 16:35, jules.sagwa@matech-cameroun.com a écrit :
> Hi BATE
> 
> Find below the update status of PM progress
> 
> Regards
> 
> SAGWA TCHOUPE
> 
> Data manager
> 
> Mobile : +237 676789251
> 
>                  +237 694025988
> 
> From: jules.sagwa@matech-cameroun.com
> <jules.sagwa@matech-cameroun.com>
> Sent: Thursday, August 21, 2025 9:21 AM
> To: 'bate.agbor@ihstowers.com' <bate.agbor@ihstowers.com>; 'Charles
> Gnouve' <charles.gnouve@ihstowers.com>; 'moise.moukala@ihstowers.com'
> <moise.moukala@ihstowers.com>; 'Evelyne Ngonsog'
> <evelyne.ngonsog@ihstowers.com>
> Cc: 'Vensa Mohamadu' <vensa.mohamadu@ihstowers.com>;
> 'lilian.vensu@matech-cameroun.com' <lilian.vensu@matech-cameroun.com>;
> 'Amza Njatono' <amza.njatono@matech-cameroun.com>; 'SyprienTanzi'
> <syprien.tanzi@matech-cameroun.com>; 'JUDICAEL BATCHAGNIA'
> <judicael.batchagnia@matech-cameroun.com>; 'Konkep Stephane'
> <stephane.nkonkep@matech-cameroun.com>; 'Herve Iroume'
> <herve.iroume@matech-cameroun.com>; 'Alphonse K. Deufo'
> <alphonse.deufo@ihstowers.com>; 'Eko Mvondo Andre Patrick'
> <andre.eko@matech-cameroun.com>; 'Dominique Assako'
> <dominique.assako@ihstowers.com>
> Subject: RE: MOM between IHS CENTER - MATECH
> 
> Hi BATE
> 
> The file is attached for your refence.
> 
> Tanks for all various supports.
> 
> Air Conditioner
> 
> ATS
> 
> Fire Extinguisher
> 
> General
> 
> Generator
> 
> Grid
> 
> Passive Cabinet
> 
> Shelter
> 
> Solar
> 
> Tank
> 
> Tower
> 
> Grand Total
> 
> 192
> 
> 148
> 
> 462
> 
> 568
> 
> 385
> 
> 570
> 
> 637
> 
> 188
> 
> 9
> 
> 107
> 
> 348
> 
> 3614
> 
> Cancelled
> 
> 3
> 
> 4
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 14
> 
> Closed Complete
> 
> 189
> 
> 148
> 
> 458
> 
> 567
> 
> 384
> 
> 569
> 
> 636
> 
> 187
> 
> 9
> 
> 106
> 
> 347
> 
> 3600
> 
> Awaiting Execution
> 
> 37
> 
> 42
> 
> 41
> 
> 271
> 
> 152
> 
> 226
> 
> 260
> 
> 34
> 
> 9
> 
> 100
> 
> 31
> 
> 1203
> 
> Assigned
> 
> 25
> 
> 34
> 
> 38
> 
> 203
> 
> 126
> 
> 187
> 
> 205
> 
> 22
> 
> 3
> 
> 85
> 
> 26
> 
> 954
> 
> Work In Progress
> 
> 11
> 
> 8
> 
> 3
> 
> 67
> 
> 26
> 
> 39
> 
> 54
> 
> 12
> 
> 6
> 
> 15
> 
> 5
> 
> 246
> 
> Ready
> 
> 1
> 
> 1
> 
> 1
> 
> 3
> 
> Awaiting Review
> 
> 7
> 
> 16
> 
> 8
> 
> 58
> 
> 49
> 
> 48
> 
> 71
> 
> 90
> 
> 1
> 
> 147
> 
> 10
> 
> 505
> 
> Work In Progress
> 
> 7
> 
> 16
> 
> 8
> 
> 58
> 
> 49
> 
> 48
> 
> 71
> 
> 90
> 
> 1
> 
> 147
> 
> 10
> 
> 505
> 
> Grand Total
> 
> 236
> 
> 206
> 
> 511
> 
> 897
> 
> 586
> 
> 844
> 
> 968
> 
> 312
> 
> 19
> 
> 354
> 
> 389
> 
> 5322
> 
> Validate Complete
> 
> 80.08%
> 
> 71.84%
> 
> 89.63%
> 
> 63.21%
> 
> 65.53%
> 
> 67.42%
> 
> 65.70%
> 
> 59.94%
> 
> 47.37%
> 
> 29.94%
> 
> 89.20%
> 
> 67.64%
> 
> Awaiting IHS SS review
> 
> 2.97%
> 
> 7.77%
> 
> 1.57%
> 
> 6.47%
> 
> 8.36%
> 
> 5.69%
> 
> 7.33%
> 
> 28.85%
> 
> 5.26%
> 
> 41.53%
> 
> 2.57%
> 
> 9.49%
> 
> Generator(80%) & Tank (20%)
> 
> 58.41%		
> 
> Regards
> 
> SAGWA TCHOUPE
> 
> Data manager
> 
> Mobile : +237 676789251
> 
>                  +237 694025988
> 
> From: jules.sagwa@matech-cameroun.com
> <jules.sagwa@matech-cameroun.com>
> Sent: Monday, August 18, 2025 9:45 AM
> To: 'bate.agbor@ihstowers.com' <bate.agbor@ihstowers.com>; 'Charles
> Gnouve' <charles.gnouve@ihstowers.com>; 'moise.moukala@ihstowers.com'
> <moise.moukala@ihstowers.com>; 'Evelyne Ngonsog'
> <evelyne.ngonsog@ihstowers.com>
> Cc: 'Vensa Mohamadu' <vensa.mohamadu@ihstowers.com>;
> 'lilian.vensu@matech-cameroun.com' <lilian.vensu@matech-cameroun.com>;
> 'Amza Njatono' <amza.njatono@matech-cameroun.com>; 'SyprienTanzi'
> <syprien.tanzi@matech-cameroun.com>; 'JUDICAEL BATCHAGNIA'
> <judicael.batchagnia@matech-cameroun.com>; 'Konkep Stephane'
> <stephane.nkonkep@matech-cameroun.com>; 'Herve Iroume'
> <herve.iroume@matech-cameroun.com>; 'Alphonse K. Deufo'
> <alphonse.deufo@ihstowers.com>; 'Eko Mvondo Andre Patrick'
> <andre.eko@matech-cameroun.com>; 'Dominique Assako'
> <dominique.assako@ihstowers.com>
> Subject: RE: MOM between IHS CENTER - MATECH
> 
> Hi BATE
> 
> Find below and in attached MATECH PM tracker.
> 
> Main remarks is that all Tank PPM tasks are under I.H.S awaiting
> review.
> 
> Thus @Charles Gnouve we  are waiting for your comment to plan
> correction if necessary; even if supervisor already follow this tasks
> through WhatsApp group.
> 
> @bate.agbor@ihstowers.com note that in term of payment PPM tank is:
> 
> 	* The second most important after generator,
> 	* 2 times AC payment,
> 	* 3 times passive cabinet payment
> 	* And above all around 15 % of our global payment.
> 
> So we are now blind on all that has been said before.
> 
> Count of Number		
> 
> Air Conditioner
> 
> ATS
> 
> Fire Extinguisher
> 
> General
> 
> Generator
> 
> Grid
> 
> Passive Cabinet
> 
> Shelter
> 
> Solar
> 
> Tank
> 
> Tower
> 
> Grand Total		
> 
> 161
> 
> 115
> 
> 442
> 
> 444
> 
> 293
> 
> 448
> 
> 510
> 
> 177
> 
> 5
> 
> 1
> 
> 333
> 
> 2929		
> 
> Cancelled
> 
> 3
> 
> 4
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 1
> 
> 14		
> 
> Closed Complete
> 
> 158
> 
> 115
> 
> 438
> 
> 443
> 
> 292
> 
> 447
> 
> 509
> 
> 176
> 
> 5
> 
> 332
> 
> 2915		
> 
> Awaiting Execution
> 
> 43
> 
> 79
> 
> 57
> 
> 417
> 
> 252
> 
> 372
> 
> 422
> 
> 49
> 
> 14
> 
> 159
> 
> 48
> 
> 1912		
> 
> Assigned
> 
> 29
> 
> 72
> 
> 53
> 
> 379
> 
> 237
> 
> 358
> 
> 399
> 
> 34
> 
> 7
> 
> 157
> 
> 44
> 
> 1769		
> 
> Work In Progress
> 
> 13
> 
> 7
> 
> 4
> 
> 38
> 
> 15
> 
> 14
> 
> 22
> 
> 15
> 
> 7
> 
> 2
> 
> 4
> 
> 141		
> 
> Ready
> 
> 1
> 
> 1
> 
> 2		
> 
> Awaiting Review
> 
> 32
> 
> 12
> 
> 12
> 
> 36
> 
> 41
> 
> 24
> 
> 36
> 
> 86
> 
> 194
> 
> 8
> 
> 481		
> 
> Assigned
> 
> 2
> 
> 2		
> 
> Work In Progress
> 
> 32
> 
> 12
> 
> 12
> 
> 36
> 
> 41
> 
> 24
> 
> 36
> 
> 86
> 
> 192
> 
> 8
> 
> 479		
> 
> Grand Total
> 
> 236
> 
> 206
> 
> 511
> 
> 897
> 
> 586
> 
> 844
> 
> 968
> 
> 312
> 
> 19
> 
> 354
> 
> 389
> 
> 5322		
> 
> Validate Complete
> 
> 66.95%
> 
> 55.83%
> 
> 85.71%
> 
> 49.39%
> 
> 49.83%
> 
> 52.96%
> 
> 52.58%
> 
> 56.41%
> 
> 26.32%
> 
> 0.00%
> 
> 85.35%
> 
> 54.77%		
> 
> Awaiting IHS SS review
> 
> 13.56%
> 
> 5.83%
> 
> 2.35%
> 
> 4.01%
> 
> 7.00%
> 
> 2.84%
> 
> 3.72%
> 
> 27.56%
> 
> 0.00%
> 
> 54.80%
> 
> 2.06%
> 
> 9.04%		
> 
> Looking forward to your thoughts.
> 
> SAGWA TCHOUPE
> 
> Data manager
> 
> Mobile : +237 676789251
> 
>                  +237 694025988
> 
> From: lilian.vensu@matech-cameroun.com
> <lilian.vensu@matech-cameroun.com>
> Sent: Friday, August 15, 2025 12:22 PM
> To: bate.agbor@ihstowers.com
> Cc: 'Vensa Mohamadu' <vensa.mohamadu@ihstowers.com>; 'Amza Njatono'
> <amza.njatono@matech-cameroun.com>; 'SyprienTanzi'
> <syprien.tanzi@matech-cameroun.com>; 'JUDICAEL BATCHAGNIA'
> <judicael.batchagnia@matech-cameroun.com>; 'Konkep Stephane'
> <stephane.nkonkep@matech-cameroun.com>; 'Herve Iroume'
> <herve.iroume@matech-cameroun.com>; 'Alphonse K. Deufo'
> <alphonse.deufo@ihstowers.com>; jules.sagwa@matech-cameroun.com; 'Eko
> Mvondo Andre Patrick' <andre.eko@matech-cameroun.com>
> Subject: RE: MOM between IHS CENTER - MATECH
> 
> Hello Sir,
> 
> Kindly find below the list of sites with pending Grid issues.
> 
> Also find attached the sites where issues were resolved between last
> Friday and today.
> 
> Pending issues
> 
> IHS ID
> 
> Site ID
> 
> Region
> 
> Cluster
> 
> Site Name
> 
> COMMENTS ON GRID ISSUES
> 
> START DATE
> 
> Status
> 
>  Comments
> 
> IHS_YND_339
> 
> CTR_116
> 
> Centre
> 
> BARRIERE 1
> 
> Ebeba
> 
> 8 isolateurs volés sur la ligne MT
> 
> 18/04/2025
> 
> Pending
> 
> IHS_YND_369
> 
> CTR_385
> 
> Centre
> 
> BARRIERE 1
> 
> Mbeng
> 
> Fusible ouvert
> 
> 09/08/2025
> 
> Pending
> 
> IHS_YND_374
> 
> CTR_005
> 
> Centre
> 
> BARRIERE 2
> 
> Matomb
> 
> Câble ENEO coupé, Fusible ouvert
> 
> 23/04/2025
> 
> Pending
> 
> IHS_YND_377
> 
> CTR_067
> 
> Centre
> 
> BARRIERE 2
> 
> Eseka
> 
> Fusible ouvert
> 
> 02/08/2025
> 
> Pending
> 
> IHS_YND_379
> 
> T0129
> 
> Centre
> 
> BARRIERE 2
> 
> Eseka
> 
> Fusible ouvert
> 
> 02/08/2025
> 
> Pending
> 
> IHS_YND_001
> 
> T0288
> 
> Centre
> 
> ESSOS 2
> 
> Royal Hotel Yde
> 
> Câble ENEO et Distributeur cramé
> 
> 15/08/2025
> 
> Pending
> 
> IHS_YND_247
> 
> CTR_213
> 
> Centre
> 
>  MANGUIER 2
> 
> Okolo
> 
> Compteur ENEO brulé
> 
> 12/07/2025
> 
> Pending
> 
> IHS_YND_298
> 
> CTR_080
> 
> Centre
> 
> MANGUIER 2
> 
> Olembe
> 
> Mauvaises tensions ENEO
> 
> 05/07/2025
> 
> Pending
> 
> IHS_YND_316
> 
> T1551
> 
> Centre
> 
> MANGUIER 2
> 
> Nkozoa
> 
> Mauvaises tensions ENEO
> 
> 25/03/2025
> 
> Pending
> 
> IHS_YND_261
> 
> CTR_237
> 
> Centre
> 
> MENDONG 1
> 
> Barriere
> 
> Mauvaises tensions ENEO
> 
> 09/05/2025
> 
> Pending
> 
> IHS_YND_077
> 
> T0467
> 
> Centre
> 
>  MENDONG 2
> 
> Obili Carrefour
> 
> Distributeur ENEO cramé
> 
> 23/07/2025
> 
> Pending
> 
> Site sur Grid sur une phase
> 
> IHS_EDA_052
> 
> T0729
> 
> Centre
> 
> NKOLBISSON
> 
> Nyahoo
> 
> Transformateur HS
> 
> 01/06/2025
> 
> Pending
> 
> Transformateur tombé
> 
> IHS_YND_796
> 
> T1244
> 
> Centre
> 
> NKOMO
> 
> Nkoabang Ebolmedjock
> 
> ENEO low voltage
> 
>> 8months
> 
> Pending
> 
> IHS_YND_307
> 
> CTR_313
> 
> Centre
> 
> OMNISPORT
> 
> Ebogo
> 
> Mauvaises tensions ENEO
> 
> 13/07/2025
> 
> Pending
> 
> IHS_YND_308
> 
> T1548
> 
> Centre
> 
> OMNISPORT
> 
> Melen Ba'aba
> 
> ENEO low voltage
> 
> 03/03/2025
> 
> Pending
> 
> IHS_YND_328
> 
> T0055
> 
> Centre
> 
> TROPICANA 1
> 
> Nsimalen
> 
> Transformateur HS
> 
> 28/04/2025
> 
> Pending
> 
> IHS_YND_343
> 
> T1071
> 
> Centre
> 
> TROPICANA 1
> 
> Mbedoumou - Ekali
> 
> Transformateur HS
> 
> 02/06/2025
> 
> Pending
> 
> IHS_YND_283
> 
> T1281
> 
> Centre
> 
> TROPICANA 2
> 
> Abome
> 
> Compteur ENEO HS
> 
> 26/06/2025
> 
> Pending
> 
> Grid présent, Afficheur du compteur HS
> 
> Resolved issues
> 
> IHS ID
> 
> Site ID
> 
> Region
> 
> Cluster
> 
> Site Name
> 
> COMMENTS ON GRID ISSUES
> 
> START DATE
> 
> Status
> 
>  Close Date
> 
>  Comments
> 
> IHS_YND_526
> 
> T2829
> 
> Centre
> 
> NKOMO
> 
> NKOABANG2
> 
> Poteaux MT tombés
> 
> 07/08/2025
> 
> Closed
> 
> 10/08/2025
> 
> IHS_YND_684
> 
> T1406
> 
> Centre
> 
> TROPICANA 1
> 
> EKIE SUD
> 
> Compteur eneo brulé, deux fusibles cramés
> 
> 23/07/2025
> 
> Closed
> 
> 11/08/2025		
> 
> IHS_YND_545
> 
> T1497
> 
> Centre
> 
> NKOLBISSON
> 
> Nkolbisson usine des eaux
> 
> Mauvaises tensions ENEO
> 
> 02/08/2025
> 
> Closed
> 
> 11/08/2025
> 
> Phases pontées
> 
> IHS_YND_393
> 
> T0211
> 
> Centre
> 
> N'TUI
> 
> Ezezang
> 
> ENEO outage
> 
> 31/07/2025
> 
> Closed
> 
> 12/08/2025
> 
> Regards
> 
> De : lilian.vensu@matech-cameroun.com
> <lilian.vensu@matech-cameroun.com>
> Envoyé : vendredi 8 août 2025 13:02
> À : 'bate.agbor@ihstowers.com' <bate.agbor@ihstowers.com>
> Cc : 'Vensa Mohamadu' <vensa.mohamadu@ihstowers.com>; 'Amza Njatono'
> <amza.njatono@matech-cameroun.com>; 'SyprienTanzi'
> <syprien.tanzi@matech-cameroun.com>; 'JUDICAEL BATCHAGNIA'
> <judicael.batchagnia@matech-cameroun.com>; 'Konkep Stephane'
> <stephane.nkonkep@matech-cameroun.com>; 'Herve Iroume'
> <herve.iroume@matech-cameroun.com>; 'Alphonse K. Deufo'
> <alphonse.deufo@ihstowers.com>; 'jules.sagwa@matech-cameroun.com'
> <jules.sagwa@matech-cameroun.com>; 'Eko Mvondo Andre Patrick'
> <andre.eko@matech-cameroun.com>
> Objet : RE: MOM between IHS CENTER - MATECH
> 
> Hello Sir,
> 
> As requested in the last meeting, kindly find on the table below the
> list of sites with Grid issues.
> 
> IHS ID
> 
> Site ID
> 
> Region
> 
> Cluster
> 
> Site Name
> 
> COMMENTS ON GRID ISSUES
> 
> START DATE
> 
> Status
> 
>  Comments
> 
> Category
> 
>  Responsibility
> 
> IHS_YND_339
> 
> CTR_116
> 
> Centre
> 
> BARRIERE 1
> 
> Ebeba
> 
> 8 isolateurs volés sur la ligne MT
> 
> 18/04/2025
> 
> Pending
> 
> ENEO line issue
> 
> IHS
> 
> IHS_YND_374
> 
> CTR_005
> 
> Centre
> 
> BARRIERE 2
> 
> Matomb
> 
> Câble ENEO coupé, Fusible ouvert
> 
> 23/04/2025
> 
> Pending
> 
> ENEO fuse
> 
> ENEO
> 
> IHS_YND_377
> 
> CTR_067
> 
> Centre
> 
> BARRIERE 2
> 
> Eseka
> 
> Fusible ouvert
> 
> 02/08/2025
> 
> Pending
> 
> ENEO fuse
> 
> ENEO
> 
> IHS_YND_379
> 
> T0129
> 
> Centre
> 
> BARRIERE 2
> 
> Eseka
> 
> Fusible ouvert
> 
> 02/08/2025
> 
> Pending
> 
> ENEO fuse
> 
> ENEO
> 
> IHS_YND_001
> 
> T0288
> 
> Centre
> 
>  ESSOS 2
> 
> Royal Hotel Yde
> 
> Câble ENEO coupé
> 
> 16/07/2025
> 
> Pending
> 
> Immeuble en cours de démentelement
> 
> ENEO line issue
> 
> IHS
> 
> IHS_YND_316
> 
> T1551
> 
> Centre
> 
> MANGUIER 2
> 
> Nkozoa
> 
> Mauvaises tensions ENEO
> 
> 25/03/2025
> 
> Pending		
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_298
> 
> CTR_080
> 
> Centre
> 
> MANGUIER 2
> 
> Olembe
> 
> Mauvaises tensions ENEO
> 
> 05/07/2025
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_247
> 
> CTR_213
> 
> Centre
> 
>  MANGUIER 2
> 
> Okolo
> 
> Compteur ENEO brulé
> 
> 12/07/2025
> 
> Pending
> 
> ENEO meter issue
> 
> IHS
> 
> IHS_YND_261
> 
> CTR_237
> 
> Centre
> 
> MENDONG 1
> 
> Barriere
> 
> Mauvaises tensions ENEO
> 
> 09/05/2025
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_077
> 
> T0467
> 
> Centre
> 
>  MENDONG 2
> 
> Obili Carrefour
> 
> Distributeur ENEO cramé
> 
> 23/07/2025
> 
> Pending
> 
> Site sur Grid sur une phase
> 
> ENEO distributor
> 
> IHS
> 
> IHS_EDA_052
> 
> T0729
> 
> Centre
> 
> NKOLBISSON
> 
> Nyahoo
> 
> Transformateur HS
> 
> 01/06/2025
> 
> Pending
> 
> Transformateur tombé
> 
> ENEO transformer
> 
> IHS
> 
> IHS_YND_545
> 
> T1497
> 
> Centre
> 
>  NKOLBISSON
> 
> Nkolbisson usine des eaux
> 
> Mauvaises tensions ENEO
> 
> 02/08/2025
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_796
> 
> T1244
> 
> Centre
> 
> NKOMO
> 
> Nkoabang Ebolmedjock
> 
> ENEO low voltage
> 
>> 8months
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_526
> 
> T2829
> 
> Centre
> 
> NKOMO
> 
> NKOABANG2
> 
> Poteaux MT tombés
> 
> 07/08/2025
> 
> Pending
> 
> Fallen poles
> 
> ENEO
> 
> IHS_YND_393
> 
> T0211
> 
> Centre
> 
> N'TUI
> 
> Ezezang
> 
> ENEO outage
> 
> 31/07/2025
> 
> Pending
> 
> Outage
> 
> ENEO
> 
> IHS_YND_308
> 
> T1548
> 
> Centre
> 
> OMNISPORT
> 
> Melen Ba'aba
> 
> ENEO low voltage
> 
> 03/03/2025
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_307
> 
> CTR_313
> 
> Centre
> 
> OMNISPORT
> 
> Ebogo
> 
> Mauvaises tensions ENEO
> 
> 13/07/2025
> 
> Pending
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_328
> 
> T0055
> 
> Centre
> 
> TROPICANA 1
> 
> Nsimalen
> 
> Transformateur HS
> 
> 28/04/2025
> 
> Pending
> 
> ENEO transformer
> 
> ENEO
> 
> IHS_YND_343
> 
> T1071
> 
> Centre
> 
> TROPICANA 1
> 
> Mbedoumou - Ekali
> 
> Transformateur HS
> 
> 02/06/2025
> 
> Pending
> 
> ENEO transformer
> 
> ENEO
> 
> IHS_YND_684
> 
> T1406
> 
> Centre
> 
> TROPICANA 1
> 
> EKIE SUD
> 
> Compteur eneo brulé, deux fusibles cramés
> 
> 23/07/2025
> 
> Pending
> 
> Absence de deux phases
> 
> Grid phase
> 
> IHS
> 
> IHS_YND_283
> 
> T1281
> 
> Centre
> 
> TROPICANA 2
> 
> Abome
> 
> Compteur ENEO HS
> 
> 26/06/2025
> 
> Pending
> 
> Grid présent, Afficheur du compteur HS
> 
> ENEO meter issue
> 
> IHS
> 
> Kind regards.
> 
> De : jules.sagwa@matech-cameroun.com <jules.sagwa@matech-cameroun.com>
> 
> Envoyé : vendredi 8 août 2025 12:03
> À : 'Eko Mvondo Andre Patrick' <andre.eko@matech-cameroun.com>;
> bate.agbor@ihstowers.com
> Cc : 'Vensa Mohamadu' <vensa.mohamadu@ihstowers.com>; 'Amza Njatono'
> <amza.njatono@matech-cameroun.com>; 'SyprienTanzi'
> <syprien.tanzi@matech-cameroun.com>; 'JUDICAEL BATCHAGNIA'
> <judicael.batchagnia@matech-cameroun.com>; 'Konkep Stephane'
> <stephane.nkonkep@matech-cameroun.com>; 'Herve Iroume'
> <herve.iroume@matech-cameroun.com>; 'Vensu Lilian'
> <lilian.vensu@matech-cameroun.com>; 'Alphonse K. Deufo'
> <alphonse.deufo@ihstowers.com>
> Objet : RE: MOM between IHS CENTER - MATECH
> 
> Hi Boss
> 
> Find in attached and below the PM progress status, also the tracker
> where site are being followed.
> 
> Regards
> 
> SAGWA TCHOUPE
> 
> Data manager
> 
> Mobile : +237 676789251
> 
>                  +237 694025988
> 
> From: jules.sagwa@matech-cameroun.com
> <jules.sagwa@matech-cameroun.com>
> Sent: Thursday, August 7, 2025 3:03 PM
> To: Eko Mvondo Andre Patrick <andre.eko@matech-cameroun.com>;
> bate.agbor@ihstowers.com; Alphonse K. Deufo
> <alphonse.deufo@ihstowers.com>; Herve Iroume
> <herve.iroume@matech-cameroun.com>; Konkep Stephane
> <stephane.nkonkep@matech-cameroun.com>; 'Vensu Lilian'
> <lilian.vensu@matech-cameroun.com>; JUDICAEL BATCHAGNIA
> <judicael.batchagnia@matech-cameroun.com>; SyprienTanzi
> <syprien.tanzi@matech-cameroun.com>
> Cc: Vensa Mohamadu <vensa.mohamadu@ihstowers.com>; 'Amza Njatono'
> <amza.njatono@matech-cameroun.com>
> Subject: MOM between IHS CENTER - MATECH
> 
> Hi All
> 
> Below the minutes of meetings of Wednesday between IHS center and
> MATECH.
> 
> Agenda
> 
> 	* Flow chart presentation.
> 	* PM validation process with I.H.S.
> 	* Work flow presentation.
> 
> Flow chart, the initial one is presented, and require improvement
> because many recent movement in the company.
> 
> Alphonse comment the Chart :
> 
> 	* By query of the chart through the use of MATECH supervisor.
> 	* The understanding of the project requirements, specially concerning
> outages.
> 	* He suggest also to prepare and share statistics (NOC-PM-FUEL) to
> technician for them to understand and feel the impact of theirs
> actions and/or performances.
> 
> RM recommend that :
> 
> 	* Technicians and specially supervisors should be trained on others
> aspects of the maintenance, like automation, power cabinet
> configuration and others.
> 
> Work flow organization, on this question :
> 
> 	* MATECH should encourage technician to organize and specially share
> the work to make it goes as fast as possible.
> 	* MATECH management should make oil and consumable always available.
> 	* All the MATECH office representative should be in the I.H.S group
> of PM validation, and Jules should share every Friday the progress of
> PM execution - PM validation and all other related.
> 	* On Fuel, every Friday Liliane should share ENEO issues on sites and
> Stephane share the Critical site from CMS.
> 	* On HSE Syprien should share all necessary report with I.H.S and
> specially follow the first safety requirements on site.
> 
> PM realization Herve raise that the new Jubaly Brothers generator are
> not well design and most of them present abnormal behavior at less
> than 100 hours of working time, detailed report is awaited on
> Wednesday.
> 
> Miscellaneous Alphonse require that MATECH should set mechanism to
> provide spares spontaneously.
> 
> Regards
> 
> SAGWA TCHOUPE
> 
> Data manager
> 
> Mobile : +237 676789251
> 
>                  +237 694025988